Solar equipment maker sues VI Electron for $860,000 over unpaid solar farm inverters on St. Croix

Christian Loranger, CEO of VI Electron, speaks during the June 13, 2025, ribbon-cutting ceremony for the Hogensborg Solar Farm on St. Croix, as Karl Knight, CEO of the Virgin Islands Water and Power Authority, left, and Governor Albert Bryan Jr. look on. A federal lawsuit filed Monday alleges that VI Electron failed to pay the full amount owed for inverter equipment installed at the solar farm.
Government House Facebook page
Christian Loranger, CEO of VI Electron, speaks during the June 13, 2025, ribbon-cutting ceremony for the Hogensborg Solar Farm on St. Croix, as Karl Knight, CEO of the Virgin Islands Water and Power Authority, left, and Governor Albert Bryan Jr. look on. A federal lawsuit filed Monday alleges that VI Electron failed to pay the full amount owed for inverter equipment installed at the solar farm.

ST. CROIX — A Massachusetts-based solar equipment manufacturer sued VI Electron LLC in federal court Monday, alleging the renewable energy developer owes $860,926.40 for power equipment it ordered for the Hogensborg Solar Farm on St. Croix and has not paid for in more than 21 months.
           
Solectria Renewables LLC, which does business as Yaskawa Solectria Solar, filed the complaint in the District Court of the Virgin Islands, Division of St. Thomas and St. John. The company is seeking the unpaid balance, contract interest of 1.5% per month that it calculates at not less than $263,369.23, plus attorney fees and costs, according to the complaint. It has also asked for a jury trial.
           
According to the complaint, VI Electron applied for credit with Solectria on or about February 27, 2024, in an application signed by George Owen, the company’s chief financial officer. The application lists Christian Loranger as VI Electron’s sole member and chief executive officer, and Daniel Cooney as chief operating officer. Its terms called for payment within 30 days of an invoice and interest of 1.5% per month on overdue balances and made VI Electron responsible for collection costs, the complaint states.
           
In March 2024, Solectria quoted equipment for the project under the title “Hogensborg Inverters v3,” and VI Electron issued a purchase order for the “VIElectron/STX – Hogensborg” project on or about March 21, 2024, the complaint said.
           
Solectria built and delivered seven custom-fabricated power racks, each containing eight inverters with an AC combiner, according to the filing. Inverters convert the direct current produced by solar panels into the alternating current used on the power grid. The racks were shipped to VI Electron’s freight forwarder in Medley, Florida, for transport to St. Croix, and VI Electron accepted the equipment and never rejected it, the complaint alleged.
           
Solectria invoiced VI Electron $1,198,086.40 on or about January 15, 2025, which included $1,129,940 for the power racks and $68,146.40 in tax. VI Electron paid $337,160 on or about January 31, 2025, leaving the $860,926.40 balance that became past due on or about February 14, 2025, according to the complaint.
           
The complaint, filed by St. Thomas attorney Karin Bentz, alleges that VI Electron repeatedly acknowledged the debt and promised to pay it but never did.
           
In December 2024, Owen and Loranger told Solectria the invoices would be taken care of, the complaint states. In March 2025, Owen wrote that he was aware VI Electron still had a balance of $860,926.40 from Hogensborg and that it would be included in a first milestone payment, according to the filing.
           
Over the following months, VI Electron told Solectria that the balance had been worked into construction funding for its next inverter order, that it expected a term sheet from a fund, and that the amount owed was included in the budget for its next project and would be paid when financing closed, the complaint alleged. In September 2025, the company said by telephone that payment could be expected the following week, but no payment was made, according to the complaint.
           
Solectria sent a final demand letter to Loranger dated November 11, 2025, requiring payment by November 21, 2025. VI Electron has not paid any part of the balance and has never disputed the amount, the complaint alleged.
           
VI Electron signed five power purchase agreements with the Virgin Islands Water and Power Authority to supply 58 megawatts of solar power on St. Croix, St. Thomas, and St. John, Governor Albert Bryan Jr. said during his State of the Territory address in January 2024.
           
In July 2024, Loranger told the Virgin Islands Public Services Commission that major components for the Hogensborg project were arriving on island and being shipped to the site. The solar farm is located in Estate Hogensborg on St. Croix’s northwestern side, just west of Williams Delight. WAPA, Bryan, and Loranger celebrated the opening of the Hogensborg Solar Farm at a ribbon-cutting ceremony on June 13, 2025, several months after the balance on the equipment became past due, according to the complaint’s timeline.

READ MORE: PSC updated on WAPA financial crisis, solar farm projects; Ferry operators discuss suspended service

The lawsuit makes four claims: breach of contract; an action to recover the price of goods sold and delivered under the Virgin Islands version of the Uniform Commercial Code; account stated, a claim that a customer who receives a bill, keeps it without objecting, and makes a partial payment has agreed that the amount is correct; and unjust enrichment, which asks the court to award the value of the equipment if the contract is found unenforceable.

Solectria filed in federal court under diversity jurisdiction, which allows federal courts to hear disputes over more than $75,000 between parties from different states. The complaint states that Solectria, though organized in Massachusetts, is legally a citizen of Illinois because its sole member, Yaskawa America Inc., is incorporated and based there. It states that VI Electron, though organized in the Virgin Islands, is legally a citizen of Massachusetts because Loranger, its sole member, lives in Marion, Massachusetts, where the business offices of CB Loranger Companies are located.

Tom Eader is an award-winning journalist and chief reporter for WTJX with more than two decades of experience covering the Virgin Islands. A native of South Bend, Indiana, he earned a bachelor’s degree in journalism from Ball State University and moved to St. Croix in 2003 to join The St. Croix Avis, where he worked for 20 years as a reporter and photographer and served as Bureau Chief from 2013 until the paper’s closure at the beginning of 2024. He joined WTJX in January 2024, where he continues to deliver thorough, thoughtful reporting on issues important to the Virgin Islands Community. Email: teader@wtjx.org | Phone: 340-227-4463